Status of Badyar Small Hydro Power Project Regency Yamuna Energy Limited

M/s Regency Yamuna Energy Limited is a limited company incorporated on 3/4/1998 having its Regd. Office at Regency Complex, Paonta Sahib (HP) which is undertaking implementation of a licensed 4.90 MW Badyar SHP Project for which implementation agreement has been signed with the Uttaranchal Government. The project cost has been estimated as Rs.67 Cr. with term lending from State Bank of Patiala. The company has a strong background of promoters who have two similar Hydro Power Projects in Himachal Pradesh/Uttaranchal. The working Directors of the company are Sh.Arun Sharma and Sh. S.K.Jindal. 

As on 31st December 2013 the project had completed 95% of the project components needed to generation. The project has 360 meters of pipework pending and some repair work to be done on the trench weir. The Company has started the pending work and is expected to finish the project within first half of calendar year 2014.

Power evacuation : Grid connectivity to the UPCL grid was done by the two projects namely Gangani SHP and Badyar SHP who developed their own 33 KV switching station close to their project site. .
 

All Copyrights Reserved : APH Regency Power Group